| Actual Timeline- | |
| 6-nov-02 | building permit issued |
| 8-nov-02 | excavate the hole |
| 12-nov-02 | pour footings |
| 26-nov-02 | temp elec service complete |
| 2-dec-02 | poured the walls |
| 4-dec-02 | stripped the forms |
| 5-dec-02 | backfill foundation |
| 7-dec-02 | start framing |
| 21-dec-02 | framing done- tarps on roof |
| 23-dec-02 | pour the floor |
| 25-dec-02 | last window installed- weathertight |
| Plans- |
| Budget- | |
| Excavation | $ 2057 |
| foundation (materials and labor) | $ 4425 |
| electrical | |
| moving the service | $ 2018 |
| interior wiring | $ 161 |
| framing materials | $ 2281 |
| permits | $ 252 |
| roof (estimate) | $ 500 |
| siding (estimate) | $ 500 |
|
total (includes seasonal heating costs $196 that would be saved in summer) |