We're really short on storage space, so we're going to build a shop onto the garage. Easy stuff- one story with flat roof. |
There are lots of phases to this project, like- |
Actual Timeline- | |
6-nov-02 | building permit issued |
8-nov-02 | excavate the hole |
12-nov-02 | pour footings |
26-nov-02 | temp elec service complete |
2-dec-02 | poured the walls |
4-dec-02 | stripped the forms |
5-dec-02 | backfill foundation |
7-dec-02 | start framing |
21-dec-02 | framing done- tarps on roof |
23-dec-02 | pour the floor |
25-dec-02 | last window installed- weathertight |
Plans- |
Budget- | |
Excavation | $ 2057 |
foundation (materials and labor) | $ 4425 |
electrical | |
moving the service | $ 2018 |
interior wiring | $ 161 |
framing materials | $ 2281 |
permits | $ 252 |
roof (estimate) | $ 500 |
siding (estimate) | $ 500 |
total (includes seasonal heating costs $196 that would be saved in summer) |
$ 11799 |